April 23, 2024
tami sin youtube  twitter facebook

    To prevent financial losses expedite power plants procurement - PUC

    November 20, 2017

    Given the expected scale of financial losses and prospective impact going to have on the national economy, the Public Utilities Commission of Sri Lanka recommends expediting the procurement of the power plants belongs to the Least Cost Long term Generation Expansion Plans (LCLTGEP) projects in accordance with the approved schedule, as a matter of national importance.



    Reviewing the Financial Impact of Delay in Implementation of Power Plants - Generation Expansion Plan 2018-203, the Commission further pointed out that “It has to be noted that these financial loss or cost overrun figures are merely the primary outcomes of implementation delays. Cumulative effect of implementation delays over next three year period can very likely trigger a power crisis that can seriously affect the national economy.”



    “The Commission does not recommend purchasing emergency power in the future to meet any capacity or energy deficit due to implementation delays of these upcoming power plants and is of the view that such costs should not be passed through to the consumers through tariffs. The government may consider a change in industry structure if the generation plan implementation cannot be efficiently carried out within the current structure”, it added.



    The Commission further said that implementation issues pertaining to power plants identified in Least Cost Long term Generation Expansion Plans (LCLTGEP) have been prevalent over the last 20 years. Many of the identified power plants were delayed and some were not implemented at all.



    This has resulted in serious problems that have plagued the electricity sector over the past decade and seriously hampered its progress. Cost overruns and load shedding are the most prominent and direct consequences while the impact of these two factors on the economy of Sri Lanka and its competitiveness are secondary consequences. The cost overruns happen because of the expensive emergency power procurement and over dispatch of existing expensive power plants.  The  financial  loss  due  to  non-implementation/delaying  of  the approved power plants over the last 20years is enormous and the economic/impact of load shedding and high prices is much bigger.



    And the issue of implementation delays or non-implementation of power plants is not some past phenomena, but something very much prevalent even at present.



    Public Utilities Commission has been continuously monitoring the progress of the CEB in implementing the approved plan and has observed delays in the procurement process of power plants expected to be commissioned by 2020.



    Based on the information obtained from CEB the Commission expects delays in implementation of the power plants that had been approved to be implemented by 2020. A detailed implementation plan and the actual expected implementation schedule are given in the table below.

     

    Year

    Plant Additions as per LCLTGEP 18-37

    Plant Additions as per CEB

    Implementation Plans August 10, 2017

    Power Plant

    Commissioning

    Month

    Power Plant

    Commissioning

    Month

    2018

    100 MW Furnace Oil (FO)

    January 2018

    170 MW FO

    January 2018

    (Already available)

    70 MW FO

    January 2018

    100 MW FO

    August 2018

    150 MW FO

    January 2018

    50 MW (50

    plants)

    2018

    160 MW Solar

    January 2018

    60 MW (rooftop)

    2018

    15 MW Mini Hydro

    January 2018

    15 MW

    2018

    5 MW Bio Mass

    January 2018

    5 MW

    2018

     

    2019

    2× 35 MW Gas Turbines

    (GT)

    January 2019

    96 MW DG

    March 2019

    300 MW LNG

    January 2019

    122 MW Uma Oya

    January 2019

    95 MW Solar

    January 2019

    50 MW (rooftop)

    2019

    50 MW Wind

    January 2019

    15 MW Mini Hydro

    January 2019

    15 MW

    2019

    5 MW Bio Mass

    January 2019

    5 MW

    2019

    2020

    300 MW LNG

    June 2020

    1× 35 MW Gas Turbines

    January 2020

    3× 3MW GT

    January 2020

    35     MW     Broadlands

    Hydro

    January 2020

    35 MW Broadlands

    January 2020

    15     MW     Thalpitigala

    Hydro

    January 2020

    100 MW Mannar Wind

    (CEB)

    January 2020

    100 MW

    January 2020

    120 MW Wind

    January 2020

    170 MW

    (Pooneryn)

    January 2020

    105 MW Solar

    January 2020

    100 MW

    (Siyamabalanduwa)

    January 2020

    15 MW Mini Hydro

    January 2020

    15 MW

    2020

    5 MW Bio Mass

    January 2020

    5 MW

    2020

     

    Financial impact due to delaying of power plants

     

     

     

    Kerawalapitiya 300 MW Natural Gas fired power plant

     

     

    Even though the plant is expected to be commissioned in January 2019 according to the LCLTGEP, as per the CEB implementation plan it will be commissioned only in June 2020.

     

     

    Because of this commissioning delay the expensive thermal plants which are already connected to the system has to be dispatched. Thus, the additional energy cost of dispatching the expensive thermal plants is taken  as LKR 8.95 per kWh. It was assumed that the plant when commissioned, will be dispatched  at a plant factor  of 80%. Therefore if the plant is delayed by one month the energy generated at 80% plant factor will be substituted by expensive thermal power at an additional cost of LKR 8.95 per kWh.

     

     

    Considering all these factors, calculated loss for a month of delay is LKR 1.55 Billion. If the plant is going to be delayed for 18 months as per the CEB implementation plan, the loss will increase to LKR 28 Billion.

     

     

    Year

    Plant Additions as per LCLTGEP 18-37

    Plant Additions as per CEB

    Implementation Plans August 10, 2017

    Power Plant

    Commissioning

    Month

    Power Plant

    Commissioning

    Month

    2018

    100 MW Furnace Oil (FO)

    January 2018

    170 MW FO

    January 2018

    (Already available)

    70 MW FO

    January 2018

    100 MW FO

    August 2018

    150 MW FO

    January 2018

    50 MW (50

    plants)

    2018

    160 MW Solar

    January 2018

    60 MW (rooftop)

    2018

    15 MW Mini Hydro

    January 2018

    15 MW

    2018

    5 MW Bio Mass

    January 2018

    5 MW

    2018

    dgi log front

    recu

    electionR2

    Desathiya